Got stuck on this GMAT question, can anyone help me out?

Five machines at a certain factory operate at the same constant rate. If four of these machines, operating simultaneously, take 30 hours to fill a certain production order, how many fewer hours does it take all five machines, operating simultaneously, to fill the same production order?
A. 3
B. 5
C. 6
D. 16
E. 24
Read more

Asked by Karthik Iyer 5 months ago

2 Answers